Real Estate

Centre Advises 4-Month RERA Extension for Delayed Projects

Published: August 5, 2026
Author: HFT

MoHUA Advises Four-Month Extension for RERA Projects Facing Supply Chain Disruptions

The Ministry of Housing and Urban Affairs (MoHUA) has advised State Real Estate Regulatory Authorities (RERAs) to grant a four-month extension to eligible real estate projects. The relief covers projects facing delays due to global supply chain disruptions linked to the West Asia situation.

MoHUA issued the advisory on July 31, 2026. It recognises the disruption as a Force Majeure event. The situation has affected the supply of essential construction materials and delayed several real estate projects.

MoHUA Grants Four-Month Relief Under RERA

The Ministry referred to the Finance Ministry’s memorandum dated April 29, 2026. The memorandum classified the West Asia situation as a “war” for invoking the Force Majeure clause.

Under Section 6 of the Real Estate (Regulation and Development) Act, 2016, authorities can extend project registrations when events beyond developers’ control cause delays.

Therefore, the advisory recommends a four-month extension for eligible projects. This relief covers projects whose original, revised or previously extended completion dates fall on or after February 28, 2026.

State RERAs May Issue One Common Extension Order

MoHUA has also recommended a simpler process for implementing the extension.

Instead of asking developers to file separate applications, State RERAs can issue one common order covering all eligible projects.

This approach will reduce paperwork and administrative work. It will also help authorities apply the extension through a common process.

Signature Global Welcomes MoHUA’s Advisory

Welcoming the announcement, Mr. Pradeep Aggarwal, Founder and Chairman, Signature Global (India) Ltd., said:

“We wholeheartedly welcome this pragmatic and timely advisory from the Ministry of Housing & Urban Affairs. The recent global supply chain disruptions stemming from the West Asia situation have posed unprecedented, unforeseen challenges for the entire real estate sector, severely impacting the availability of critical construction materials. By invoking the Force Majeure clause and granting a four-month extension, the Government has demonstrated remarkable foresight and a deep understanding of on-ground realities. This crucial relief safeguards the industry from external shocks, allowing us to navigate these shortages without compromising on quality. Above all, it reinforces our ability to stay focused on our primary goal: delivering exceptional projects and fulfilling our promises to our valued homebuyers.”

RERA Extension Expected to Support Developers and Homebuyers

The advisory is expected to help developers manage construction delays caused by material shortages. It also provides a common framework for eligible projects across states.

Moreover, the single-order approach could reduce paperwork and avoid unnecessary delays. This may help developers focus on ongoing construction and project delivery.

Homebuyers could also benefit as delayed projects move forward under the revised timelines. Overall, the measure aims to support the real estate sector and maintain confidence in the housing market.

Related Posts

SVC Reports Strong Growth with Rs. 43,693 Crores; Reinforces Customer Trust

AI Adoption in Textiles: Data and Skills Are Key

Zen Technologies Limited Achieves Highest Dun & Bradstreet Rating of 5A1

The "Indian Tigress" Ritu Phogat Becomes a Brand Ambassador for Parimatch Sports